June 3, 2026, Construction Update
The pedestrian bridge was installed on March 20, 2026. In April and May TFord completed most of the site work, including completion of the dam repairs, final grading, and placement of topsoil. Planting and seeding are currently underway and anticipated to be completed by mid-June. Paving and guardrail installation are also anticipated to be completed by mid-June.