November 19, 2025 Construction Update

Concrete pours for the western spillway and training walls are nearing completion and expected to be complete by late November/early December. The portadam and flow-bypass that has been installed upstream of the new dam have been working well to manage water flows and maintain a dry work area on the western side of the dam. Once concrete work is complete in December, the portadam will be removed. Installation of the new pedestrian bridge is scheduled for December.  Initial work on site improvements such as the bioretention basins may occur in December, weather permitting. A construction winter shutdown is anticipated for January 2026 through April 2026. In spring 2026, final site improvements will be completed, including the new parking lots and walking paths and site plantings.