May 2025
June 2025
September 2025
September 1, 2025
The Pedestrian Bridge is scheduled for installation in September
October 2025
October 1, 2025
Planting and walkway/parking area work is scheduled for October
November 2025
November 11, 2025
Final paving and loaming and seeding
November 24, 2025
Final site clean-up
November 28, 2025